U
uktous
Member
Hi,
Using the profit criteria suggested by the code reading, the profit criteria should be defined as - accept the profit if: IRR > cost of capital, says 4%.
Suppose the NPV function of a project is 100-1.05 / (1+i)
The internal rate of return – IRR – is 5%.
IRR = 5% > COC = 4%, thus we accept the project.
Since the NPV function is upward sloping, using any discount rate lower than 5% must product a negative NPV.
Hence, if we use a discount rate equal to the cost of capital (4%), then I would produce a negative NPV = -0.96.
Using as our profit criteria, we reject the project.
I have 2 questions.
Question1:
Which profit criteria should I follow? IRR or NPV?
Question2:
Should I define the IRR profit criteria as
Accept the profit if : cost of capital > IRR
Then, if the cost of capital is 6%, we have a NPV of 0.94.
Both IRR and NPV criteria are past, but the project can’t product a return required by shareholder.
Using the profit criteria suggested by the code reading, the profit criteria should be defined as - accept the profit if: IRR > cost of capital, says 4%.
Suppose the NPV function of a project is 100-1.05 / (1+i)
The internal rate of return – IRR – is 5%.
IRR = 5% > COC = 4%, thus we accept the project.
Since the NPV function is upward sloping, using any discount rate lower than 5% must product a negative NPV.
Hence, if we use a discount rate equal to the cost of capital (4%), then I would produce a negative NPV = -0.96.
Using as our profit criteria, we reject the project.
I have 2 questions.
Question1:
Which profit criteria should I follow? IRR or NPV?
Question2:
Should I define the IRR profit criteria as
Accept the profit if : cost of capital > IRR
Then, if the cost of capital is 6%, we have a NPV of 0.94.
Both IRR and NPV criteria are past, but the project can’t product a return required by shareholder.